Authored By: Realeboha Ditshwane
University of the Witwatersrand
Introduction
The Gerolomou case is a significant decision in South African contract law. It deals with the intersection of compromise, undue influence, and improperly obtained consensus. The case is important for its treatment of unconscionability in commercial relationships. It addresses situations where a stronger party withholds an admitted debt to pressure a weaker party into surrendering contractual rights.
What is unsettling about the judgement is that the court departed from established precedent. It failed to provide legal clarity and instead created uncertainty. The court did not recognise economic duress as an independent ground for rescission in South African law. Consequently, it missed an opportunity to adopt a clearer and more modern doctrinal approach. Such recognition could have better protected vulnerable parties against unconscionable commercial pressure.
Facts of the case
The case concerns Derek Van Wyk, a subcontractor who performed specialised work for the defendant, Gerolomou Constructions (Pty) Ltd.[1] The parties concluded an oral agreement between April and June 2002.[2] In terms of the agreement, the Plaintiff was required to design and install four wooden corner structures for the Nan Hua Temple.[3] He delivered his performance in accordance with the agreement.[4] However, the Defendant withheld payment of R48,523.54.[5] As a result, the plaintiff was placed in severe financial distress due to the defendant withholding the payment.[6] The plaintiff was under significant pressure from their workers who were awaiting payment.[7]
Moreover, the funds required to pay the workers were expected from the defendant.[8] The defendant was aware of the plaintiff’s financial position. Furthermore, the defendant knew that payment would relieve this distress.[9] The plaintiff was also not in a position to institute legal proceedings at the time.[10] On 16 October 2002,[11] the parties met to negotiate payment.[12] The defendant’s representatives presented a document titled ‘Final Account’ which acknowledged the full retention debt.[13] However, it only reflected a remaining balance of R19,291.70 because of alleged contra charges.[14] The plaintiff protested that the charges were unfair.[15] The plaintiff was informed that they had to sign the document or receive no payment at all.[16] His financial position led him to sign the documents.[17] The Plaintiff later argued that the settlement was not a valid contract of compromise because the signature was obtained under undue influence.[18]
III. Issue
The issue before the court was whether the defendant’s threat to breach the contract constituted unconscionable conduct.
Arguments presented
Plaintiff’s arguments
The plaintiff contended that the ‘Final Account’ document, which was signed by the respondent constituted a valid contract of compromise.[19] They argued that by signing the document and accepting payment of R19,291.70, the respondent had agreed to a full and final settlement of all outstanding claims arising from the subcontracting work.[20] The plaintiff relied on the precedent established in Be Bop A Lula Manufacturing & Printing CC v Kingtex Marketing (Pty) Ltd.[21] They argued that an admission of liability for a specific amount does not prevent a proposal from being construed as an offer of compromise.[22] The document was a commercial proposal which the respondent was free to accept or reject.[23] Furthermore, the respondent’s signature constituted binding consensus to resolve the dispute regarding the contra charges.[24]
Defendant’s arguments
The respondent argued that the settlement agreement was voidable because his signature had been obtained through undue influence.[25] He relied on Patel v Grobbelaar 1974 (1) SA 532 (A), to prove that there was undue influence.[26] He contended that he was in severe financial distress and under significant pressure to pay his workers.[27] The plaintiff was aware of this vulnerable position and held economic power over him due to the withheld payment.[28] The Plaintiff intentionally delayed payment.[29] Furthermore, they used this pressure to weaken the Defendant’s ability to exercise independent and free judgment when entering into the agreement.[30]
Court’s reasoning and analysis
The court found no valid compromise agreement existed.[31] Furthermore, the parties lacked genuine consensus[32]. A valid contract requires clear offer and acceptance.[33] However, the defendant made no genuine commercial offer. Instead, it imposed conditions before releasing admitted funds.[34] Moreover, the court applied the principles established in Absa Bank Ltd v Van der Vyver NO. It distinguished compromise from payment of an admitted liability.[35] The document admitted that R19,291.70 remained due.[36] Consequently, the settlement clause lacked binding force.[37] Furthermore, the court distinguished the Bebop case.[38] In the present matter, pressure accompanied the admitted debt.[39] The defendant used payment as leverage against the plaintiff.[40] Accordingly, the court rejected the alleged compromise agreement.[41]
Even if a contract existed, the court found it voidable for undue influence.[42] Moreover, the court applied the four-part test from Patel v Grobbelaar.[43] The test considered influence, malleable will, unconscionability, and manifest prejudice.[44] The court found a clear imbalance of economic power between the parties.[45] Furthermore, the plaintiff was in severe financial distress.[46] His workers were waiting at the construction site for payment.[47] However, the defendant continued delaying the release of funds.[48] Consequently, the plaintiff’s ability to exercise free judgment became weakened.[49] The court examined the meaning of unconscionable conduct by relying on the Australian case, Commercial Bank of Australia v Amadio (1983) HCA 14.[50] The court held that unconscionability involves taking unfair advantage of another’s financial weakness.[51] Furthermore, it includes exploiting a party unable to protect their own interests.[52]
Judgement and ratio Decidendi
The court clarified that genuine disputed settlement may involve economic pressure.[53] However, withholding an admitted debt is unconscionable conduct.[54] This is especially true where accrued contractual rights are surrendered.[55] Finally, the court linked its reasoning to constitutional values by referring to Barkhuizen v Napier (2007) 5 SA 323 CC. The court noted that pacta sunt servanda relates to dignity and freedom. However, the defendant’s conduct undermined these constitutional principles by it infringing the plaintiff’s section 34 right to fair adjudication under the Constitution of the Republic of South Africa, 1996.[56] Judge Tuchten, with judge Claassen concurring, upheld the magistrate’s decision in favour of the plaintiff.[57]
VII. Critical Analysis
CJ Pretorius and R Ismail argue that Gerolomou should have recognised economic duress rather than undue influence.[58] Furthermore, they criticise the court’s rejection of compromise and technical approach to pleadings.[59] Although the outcome was fair, they contend that legal certainty and doctrinal coherence were weakened in South African contract law.[60]
To add on the above contentions; The judgment in Gerolomou departs from the traditional requirement of a pre-existing relationship of trust, when applying undue influence.[61] Furthermore, the facts indicate clear pressure at the time of signing.[62] The plaintiff himself stated that he was under pressure when he signed the document.[63] Moreover, he protested against the agreement.[64]
The requirements as stated in Broodryk v Smuts NO (1942) TPD 47, are actual violence or reasonable fear.[65] In this case, the fear was economic. The plaintiff feared non-payment and inability to pay workers. Consequently, his business stability was threatened. Secondly, the threat must be directed at the person or their property.[66] Here, it targeted economic interests. Non-payment meant inability to pay workers. This risk extended to business collapse. Thirdly, the threat must be imminent or inevitable.[67] The workers were already present and waiting. The plaintiff had no realistic time to avoid the pressure. Court proceedings were also not immediately feasible due to financial constraints. Fourthly, the conduct must be contra bonos mores.[68] The defendant threatened non-payment unless the document was signed. Furthermore, using withheld admitted funds as leverage is improper. Such conduct is legally and morally unacceptable. Finally, the plaintiff suffered prejudice.[69] He forfeited part of his claim. This caused financial and business harm.
The case demonstrates that duress better explains the facts than undue influence. Moreover, the parties had no relationship of trust but operated as independent commercial entities.
The court placed greater emphasis on the economic loss suffered due to the pressure exerted on the party.[70] Furthermore, this approach highlights the centrality of financial vulnerability in the case. It therefore appears that recognition of economic duress would have been appropriate. Moreover, the court in Medscheme Holdings (Pty) Ltd v Bhamjee (2005) 5 SA 339 SCA indicated that economic duress is not yet formally established. However, it may be developed and applied in future cases. In this matter, the facts strongly support the application of economic duress. Consequently, it would have provided a clearer and more coherent legal basis for the decision.
VIII. Conclusion
The case has created confusion rather than clarity regarding pressure arising from threatened economic interests. Furthermore, the court did not apply the appropriate test to the facts. Instead, it departed from established principles and failed to properly consider the relationship between the parties. Moreover, the court did not adequately engage with relevant precedent. The decision was delivered in the High Court. However, Medscheme, a Supreme Court of Appeal decision, had already addressed similar issues. Although the facts were not identical, the case also involved economic pressure amounting to duress. The court should have followed the reasoning in Medscheme. Consequently, economic duress could have been more clearly recognised as a basis for establishing prejudice to economic interest.
Reference(S):
Cases
Gerolomou Constructions (Pty) Ltd v van Wyk (2011) 4 SA 500 GNP.
Barkhuizen v Napier (2007) 5 SA 323 CC.
Medscheme Holdings (Pty) Ltd v Bhamjee (2005) 5 SA 339 SCA.
Broodryk v Smuts NO (1942) TPD 47.
Patel v Grobbelaar (1974) 1 SA 532 A.
Commercial Bank of Australia v Amadio (1983) HCA 14.
Books
Hutchison and Pretorius (eds) “The Law of Contract in South Africa” 136 Oxford University Press 2022).
Articles
Pretorius and Ismail “Compromise, Undue Influence and Economic Duress: Gerolomou Constructions (Pty) Ltd v Van Wyk 2011 (4) SA 500 (GNP)” 681-692 Obiter 681, (2012).
[1] Gerolomou Constructions (Pty) Ltd v van Wyk (2011) 4 SA 500 GNP para 1.
[2] Id. at 1.
[3] Id.
[4] Id. at 2.
[5] Id. at 6.
[6]Gerolomou Construction, supra note 1, at 6.
[7] Id.
[8] Id.
[9] Id. at 20.
[10] Id.
[11] Id. at 6.
[12] Id.
[13] Id. at 8.
[14] Id.
[15] Id. at 7.
[16] Id. at 10.
[17] Id. at 6.
[18] Id. at 3.
[19]Gerolomou Construction, supra note 1, at 2.
[20] Id. at 2-3.
[21] Id. at 15.
[22] Id. at 15-16.
[23] Id. at 10.
[24] Id. at 15.
[25] Id. at 4.
[26] Id. at 19.
[27]Id. at 4.
[28] Id.
[29] Id. at 20.
[30]Id. at 20.
[31] Gerolomou Construction, supra note 1, at 10.
[32] Id.
[33] Id.
[34] Id.
[35] Id. at 12.
[36] Id. at 14.
[37] Id.
[38] Id. at 16.
[39] Id.
[40] Id.
[41] Id.
[42] Id. at 17-18.
[43] Id. at 19.
[44] Id.
[45] Id.
[46] Id.
[47] Id.
[48] Id. at 21
[49] Id.
[50] Gerolomou Construction, supra note 1, at 23.
[51] Id.
[52] Id.
[53] Id. at 24
[54] Id.
[55] Id.
[56] Id.
[57] Id.
[58] Pretorius and Ismail “Compromise, Undue Influence and Economic Duress: Gerolomou
Constructions (Pty) Ltd v Van Wyk 2011 (4) SA 500 (GNP)” 681-692 Obiter 681, 691(2012).
[59]Id. at 685.
[60] Id. at 692
[61] PRETORIUS AND ISMAIL 688.
[62] Gerolomou Construction, supra note 1, at 7.
[63] Id. at 4.
[64] Id. at 7.
[65] HUTCHISON AND PRETORIUS (EDS) “THE LAW OF CONTRACT IN SOUTH AFRICA” 136 OXFORD UNIVERSITY PRESS 2022).
[66] HUTCHISON AND PRETORIUS (EDS) “THE LAW OF CONTRACT IN SOUTH AFRICA 138 (2022).
[67] Id. at 138.
[68] Id. at 139.
[69] Id. at 139.
[70] Gerolomou Construction, supra note 1, at 24.

